Here are some photos showing what's happening on the the Anson Field.

25 June 2019: The roof trusses are being hoisted into poisition on the new hall.

22 May 2019: The concrete base of the new hall has set, and work has started making the shuttering for the next stage - the concrete upstands for the walls where the vertical reinforcing is currently showing

22 May 2019: The concrete has been poured to form the foundations for the 5 houses south of the nursery

22 May 2019: The nursery now has walls and roof trusses

21 May 2019: The concrete base of the new hall is now complete and level

21 May 2019: Smoothing the contrete base of the new hall

21 May 2019: Spraying the concrete into the steelwork which forms the base of the new hall

21 May 2019: The concrete is being poured to form the base of the new hall

19 May 2019: The steelwork which forms the base of the new hall is ready to be covered in concrete

9 May 2019: the walls are erected for the new nursery building

3 May 2019: representatives from MCG and the Parish Council visit the site each month to review progress

3 Apr 2019: work is steaming ahead putting down tarmac for the new road

26 Mar 2019: the old Marcham Sports, Scouts and Social Club has gone. The old Nursery building (to the right) will remain until the new Nursery is completed

26 Mar 2019: the old Marcham Sports, Scouts and Social Club is being demolished to make way for the new Village Hall

14 Mar 2019: work has started on the road which will lead to the five new houses on the east of the site

14 Mar 2019: shuttering for the slab base of the new Nursery building is in place and the concrete has been poured

5 Mar 2019: work continues on the footings for the new Nursery

4 Mar 2019: trenches which will be part of the footings for the new Nursery are being filled with hard core and levelled

27 Feb 2019: moving assembled steel reinforcing sections for the base of the new Nursery building

20 Feb 2019: work proceeding on the main foul drain

19 Feb 2019: Thomas Homes office and store cabins in place

17 Feb 2019: ground levelled and compacted for the office blocks to arrive

6 Feb 2019: SSE installing the electric supplies to the site (trenches and conduit being pulled through) - and cutting through a resident's drive!

6 Feb 2019: preparing the site ready to install the electric supplies